On February 17, 2026 a public bid opening was held for Bid Package # 1 for the Sheriff's Office/Jail project, which includes site, precast, detention, and elevator contracts. The Elevator contract to be re-bid due to a specification error.
On March 3, 2026 the Property Committee recommended awarding contracts for Detention Equipment, Site work, and Precast concrete.
On March 9, 2026 a public bid opening was held for the re-bid of the Elevator contract from Bid Package #1.
On March 10, 2026 the Property Committee recommended awarding a contract for Elevator.
Subcontractor | Bid Unit | Bid Amount |
Mid-States Concrete Industries | Precast Concrete (Furnish only) | $3,495,794 |
Stronghold Industries, Inc. | Detention Equipment (Furnish and Installed) | $5,776,000 |
Schumacher Elevator Company | Hydraulic Elevator (Furnished and installed) | $180,833 |
R.G. Huston Co., Inc | Grading, Earthwork, and Utilities (Furnished and installed) | $7,424,000 |
| Total: | $16,876,627 |